This project involved the replacement of sand filter media in the wastewater treatment plant (WWTP) serving the plating TC2W process at PT Suzuki Indomobil Motor Plant Tambun I. The work aimed to restore filtration performance that had decreased due to prolonged operation. All activities were completed within a short execution period without disrupting plant operations. Process reliability and treatment continuity were key priorities.
Project Objective
The objective of this project was to restore the effectiveness of the primary filtration unit by replacing worn sand filter media, ensuring stable wastewater treatment performance, and supporting environmental compliance.
Project Scope
Assessment of Existing Sand Filter Media
Evaluation of media condition and filtration performance
Identification of replacement requirements
Confirmation of suitable media specifications
Sand Filter Media Replacement
Removal and disposal of existing sand media
Internal cleaning of the filter vessel
Installation of new sand filter media
Media Arrangement and Distribution
Proper layering and uniform media distribution
Adjustment of media thickness
Prevention of channeling within the filter
System Inspection and Initial Testing
Inspection of flow rate and operating pressure
Verification of filtration performance
Minor system adjustments if required
Key Outcomes
Restored wastewater filtration efficiency
Stable and reliable WWTP operation
Improved consistency of treated wastewater quality
Continued support for environmental compliance
PT Suzuki Indomobil Motor Plant Tambun I
Tambun, Bekasi
June 18, 2024
2 Days
Automotives
Explore more of our completed projects
Our team of experts is ready to help you achieve your operational goals