Install Lab Room WWTP Painting

Water & Waste Water Treatment (EPC)

March 21, 2025

Tambun, Bekasi

project-img

Project Overview

This project involved the installation of a laboratory room within the Wastewater Treatment Plant (WWTP) at PT Suzuki Indomobil Motor Plant Tambun I. The laboratory was developed to support wastewater quality monitoring and testing activities in accordance with environmental and industrial standards.
The work included room installation, finishing and painting, as well as the supply and installation of laboratory equipment. All activities were executed with careful coordination to ensure seamless integration with existing WWTP operations.

Project Objective
The objective of this project was to strengthen wastewater quality control by providing a dedicated laboratory facility within the WWTP. The laboratory was designed to support accurate testing, efficient analysis, and regulatory compliance in support of automotive manufacturing operations.

Project Scope

  1. Laboratory Planning and Design

    • Alignment of laboratory layout with WWTP operational requirements

    • Space planning to support safe and efficient wastewater testing

    • Integration with existing WWTP facilities

  2. Laboratory Room Installation and Finishing

    • Installation of the laboratory room

    • Finishing and painting works in accordance with industrial standards

    • Implementation of safety and workplace comfort aspects

  3. Supply and Installation of Laboratory Equipment

    • Selection of laboratory equipment based on wastewater testing parameters

    • Installation and arrangement of laboratory instruments

    • Configuration to support effective analytical processes

  4. System Integration and Functional Testing

    • Integration of laboratory facilities with the WWTP system

    • Functional testing of room facilities and equipment

    • Verification of operational readiness before handover


Key Outcomes

  • Enhanced wastewater quality monitoring capability

  • Improved reliability and efficiency of WWTP testing activities

  • Laboratory facility ready for operational use

  • Support for environmental compliance and operational excellence

Project Gallery

gallery
gallery
gallery
gallery
gallery
gallery
gallery
gallery

Project Information

Client

PT Suzuki Indomobil Motor Plant Tambun I

Location

Tambun, Bekasi

Start Date

March 21, 2025

Duration

32 Days

Industry

Automotives