Project Overview

This project involved the reconditioning of the plating wastewater treatment system at PT Suzuki Indomobil Motor Plant Tambun I through the replacement of critical equipment. The work focused on restoring system performance and operational reliability by replacing aging pumps and agitator motors.
All activities were carefully executed to ensure continuity of plant operations while improving treatment process stability.

Project Objective
The objective of this project was to enhance the reliability and operational stability of the plating wastewater treatment process by upgrading key mechanical components. The reconditioning aimed to reduce operational risk, improve mixing efficiency, and support consistent wastewater treatment performance within the automotive manufacturing environment.

Project Scope

  1. System Assessment and Engineering Review

    • Evaluation of the existing plating wastewater treatment equipment condition

    • Identification of pump and agitator motor performance degradation

    • Alignment of replacement equipment specifications with system requirements

  2. Replacement of Pumps and Agitator Motors

    • Supply of new pumps and agitator motors

    • Dismantling of existing equipment

    • Installation in accordance with technical and safety standards

  3. Mechanical and Electrical Integration

    • Mechanical and electrical connection adjustments

    • Integration with existing control and power systems

    • Verification of installation accuracy and compatibility

  4. Functional Testing and Performance Verification

    • Operational testing of pumps and agitators

    • Verification of system stability and performance

    • Confirmation of improved operational efficiency


Key Outcomes

  • Improved reliability of the plating wastewater treatment system

  • More stable and efficient wastewater treatment operation

  • Reduced risk of unplanned equipment downtime

  • Support for sustainable and compliant automotive manufacturing operations

Project Gallery

gallery
gallery
gallery
gallery
gallery
gallery

Project Information

Client

PT Suzuki Indomobil Motor Plant Tambun I

Location

Tambun, Bekasi

Start Date

August 29, 2024

Duration

19 Days

Industry

Automotives