September 06, 2025
Tambun, Bekasi
This project involved the replacement of sand and activated carbon filter media for a 10 m³/h demineralized water system at the plating TC2W facility of PT Suzuki Indomobil Motor Plant Tambun I. The work was conducted to restore filtration performance that had declined due to long-term operation. All activities were completed within a short execution period without disrupting plant operations. Maintaining consistent water quality for plating processes was the main focus.
Project Objective
The objective of this project was to restore filtration efficiency and ensure stable demineralized water quality by replacing worn sand and activated carbon media. The project aimed to support reliable plating operations and maintain overall system performance.
Project Scope
Assessment of Existing Filter Media
Evaluation of sand and activated carbon media condition
Identification of performance degradation
Confirmation of suitable replacement specifications
Sand and Activated Carbon Media Replacement
Removal and disposal of existing filter media
Internal cleaning of filter vessels
Installation of new sand and activated carbon media
Media Arrangement and Distribution
Proper media layering and uniform distribution
Adjustment of media thickness and configuration
Prevention of channeling inside the filter system
System Inspection and Initial Testing
Inspection of flow rate and operating pressure
Verification of filtration performance
Minor system adjustments after replacement
Key Outcomes
Restored filtration efficiency
Stable demineralized water quality for plating processes
Improved reliability of the demineralization system
Minimal downtime with no disruption to plant operations
PT Suzuki Indomobil Motor Plant Tambun I
Tambun, Bekasi
September 06, 2025
2 Days
Automotives